Hi. I'm currently in the process of implementing time tracking in JIRA and scratching my head a bit.

We have a required to require that any assignee logs work to a task and any associated sub-tasks. The issue I have is users are raising parent task with set hours (e.g. 80hrs) then creating sub-tasks to break down the parent task (e.g. 4 sub-tasks with 20hrs each).

When the overall task is completed we end up with 40hrs logged but 80hrs estimated.

Is there any solution to this? Ive managed to only estimate on parent and reconfigure sub-tasks to prevent estimations but enforce time logging, and allow that to roll up. However to close the main task I still have to enter 0.1m as logging is a required field. I could make it an optional field but in many cases the parent task may not have sub-tasks and still needs time tracking enforced.


Can someone help as im not sure how to resolve this issue
Thanks

0 answers

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Apr 17, 2018 in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

800 views 2 19
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you