Reporting

Vinod Kumar May 11, 2022

Hi Team,

 I have got three requirements as below where reports need to be generated

1. creating the Burndown report which details need  

is as follows

X-axis - Due Date

Y-Axis- Issues Count Resolved or Open

2. Open closure rate per week- In this need Bar graph or Pie chart where Open and closed tickets need to be done

3. Open or Pending Issues per user Like Bar Graph  or  Assignee graph. The above are the requirements . Can you suggest whether it is possible to create as mentioned above in Burndown. And also suggest for the rest two requirement

 

1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 11, 2022

That is not a burn down chart.  A burn down measures the what the team has completed against what they committed to do, based on the estimates that were on the cards when the sprint was started.

Have a look at the "control chart" instead

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
FREE
PERMISSIONS LEVEL
Site Admin
TAGS
AUG Leaders

Atlassian Community Events