The current configuration in JIRA Reports for  Burndown charts is on the basis of total time/effort spent OR time remaining on the user story. 

How can we configure JIRA to generate reports on the basis of user story points consumed ? 

e.g if i have a story of 10 user points and on the 3rd day I have finished work equivqlent to 3 story points, I  should be able to mark progress on the user story as 3 points completed and the burn-down-chart should be generated accordingly. 

1 answer

0 votes
GabrielleJ
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 3, 2015

There should be a configuration in your Agile Board to change this: 

  • Open your SCRUM board and click on "Board >> Configure"
  • Click on the "Estimation" tab 
  • Change Time Tracking to your need
  • Change the value of the "Estimation Statistic" (If needed)

 