Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Next challenges

Recent achievements

  • Global
  • Personal

Recognition

  • Give kudos
  • Received
  • Given

Leaderboard

  • Global

Trophy case

Kudos (beta program)

Kudos logo

You've been invited into the Kudos (beta program) private group. Chat with others in the program, or give feedback to Atlassian.

View group

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

Report to show missing status

I not sure if this can be done or not, 

I recently noticed a lot of our dev work has gone straight into UAT or Production with out any QA work being done.

I need a to find away to historically go back and see what jiras have dev work done but never had a status of and kind of QA 

an example of this is i am looking at one JIRA all kinds of dev work was done and deployed but there is no QA 

thats the info I am looking for 

1 answer

0 votes

Hello @Michael Littlewood

I would go with something like:

project = MYPROJECT AND status WAS "QA Work" BEFORE "2021-01-01"

That way you can find all the issues within a project that have been in a particular status before a particular date (stating the future will give you all the past).
🚀

Suggest an answer

Log in or Sign up to answer
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you