Hi
i am using JIRA for my product backlog which has 3 teams working on it with sprints running in parallel.
when i go to reports and take release burndown report, it shows wrong information like in one sprint trinity sprint15 it doesn't show any work completed for 7.0.0 although in sprint report it shows the done.
also i noticed that jira items are shown in wrong sprintno , but if i select the item and open it is shows the right sprint no
If the burndown only looks at a single project, try reindex the project via the dropdown menu in the top right corner of the project configuration. If the burndown spams more projects, you might want to reindex the whole instance. Make sure to do this when you have little traffic coming to Jira, as this can take hours on larger instances.
This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.
Read moreHey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...
Connect with like-minded Atlassian users at free events near you!
Find a groupConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no AUG chapters near you at the moment.
Start an AUGYou're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.