Relationship between story points and time tracking

Hi All,

What is the relationship between story points and time tracking?

Secondly, if I am using time tracking, can I view the velocity in terms of time tracked?

Where can I find more info about this? I am having a difficult time understanding how time tracking and story points work in relation to velocity and burn down. 

Thanks.

1 answer

This widget could not be displayed.

There is no relationship.  Story points are a measure of complexity, and time-tracking is about estimating how long something might take and who has logged work on the task.

Time tracking is a very valid thing to base your Velocity on - set your board to look at the time estimates and it will work fine.

But bear in mind that you can't work with two sets of estimates.  For any team, pick Story Points, Time estimates, or another numeric measure and stick to it.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

200 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you