Relationship between story points and time tracking

Hi All,

What is the relationship between story points and time tracking?

Secondly, if I am using time tracking, can I view the velocity in terms of time tracked?

Where can I find more info about this? I am having a difficult time understanding how time tracking and story points work in relation to velocity and burn down. 

Thanks.

1 answer

1 votes

There is no relationship.  Story points are a measure of complexity, and time-tracking is about estimating how long something might take and who has logged work on the task.

Time tracking is a very valid thing to base your Velocity on - set your board to look at the time estimates and it will work fine.

But bear in mind that you can't work with two sets of estimates.  For any team, pick Story Points, Time estimates, or another numeric measure and stick to it.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

2,760 views 11 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot