Record Sprint Points

Hi, 

is there any place in JIRA Agile, perhaps within the Reports section, where you can find the number of actual points that have been completed within the past sprints. 

In other words, my current sprint shows the actual number of points within blue/yellow/green circles (shown in the attached file). I say actual because I do not mean only the points at the start of the sprint, but the once that were added during the sprint. After I close the sprint, are these points recorded anywhere else where I can see them?

Thanks

 

 

 

plan-points.png

 

3 answers

This widget could not be displayed.
Ollie Community Champion Nov 01, 2014
This widget could not be displayed.

Hi Ollie, thanks for the reply, but that is not correct. First, from that page:

  • The values for each issue's Estimate are recorded at the time the sprint is started. Changing the Estimate value afterwards will not be reflected in the Sprint Report.

For example in my sprint that I posted above I should have 230 points, on Sprint Report I have only 100.


Thanks

Damjan 

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Aug 06, 2018 in Jira Service Desk

A is for Activate: Share your top Jira Service Desk onboarding tips for new users!

Hi, everyone! Molly here from the Jira Service Desk Product Marketing Team :).  In the spirit of this month's  august-challenge, we're sourcing stories of Jira Service Desk activation fro...

553 views 25 15
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you