Rearranging subTaskSequence for more than one step at once?

keizie August 23, 2012

After creating subtasks, its sequences should be rearranged if other subtasks added or something.

But JIRA provide one-step-only link of sequence change. It's annoying to click multiple times.

Is there any way to change sequence of subtasks multiple steps at a time?

1 answer

1 accepted

1 vote
Answer accepted
Penny Wyatt (On Leave to July 2021)
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 23, 2012

Yes, but it's not pretty...

If you hover your mouse over the up/down arrows, you can see the URL that is called when you click the arrow.

e.g. https://<server>/secure/MoveIssueLink.jspa?id=10100&currentSubTaskSequence=0&subTaskSequence=1

id is the numeric ID of the current (parent) issue. It'll be different for whichever issue you look at.

currentSubTaskSequence is the current index of the subtask in the list that you want to move.

subTaskSequence is the new index where you want to move it to.

The sequences are numbered from 0.

So, for example, if you have a list of 10 subtasks and want to move the last subtask to the start of the list, copy the URL from any of the little arrows on your current issue, replace currentSubTaskSequence with 9, subTaskSequence with 0, paste it into the address bar and hit enter.

I said it wasn't pretty :-)

Logan G Hawkes
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 24, 2012

Taking it to the next level, has anyone scripted this? I made a half-stab at it using curl without success.

Penny Wyatt (On Leave to July 2021)
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 27, 2012

What's the generic case that you need the script for?