Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,458,136
Community Members
 
Community Events
176
Community Groups

Re abrí un Sprint, y después de cerrarlo me cambio la fecha de finalización

Tenia un Sprint ya cerrado, se re abrió para hacer un ejercicio y al cerrarlo cambio la fecha de finalización original, haciendo que aparezca en los informes actuales. Esto se puede cambiar de alguna manera ?

1 answer

0 votes
Trudy Claspill Community Leader Dec 02, 2022

Hola @Andrés Ramírez ,

Bienvenido a la comunidad.

La fecha de finalización que se muestra en el Informe de Sprint es la fecha en que se utilizó el botón Completar para el Sprint. No puedes cambiar eso. Se configura automáticamente.

Cuando vuelve a abrir un sprint, puede modificar la fecha de finalización planificada manualmente, pero esa no es la fecha que se muestra en el Informe de Sprint.