We are using Jira rapid boards and hours burndown charts to trac teams progress.
Somehow we kind of allways trying to chace ideal burndown (guideline) and feel we should but graph says are are above (so not managing it).
I did manual math and found that while sum or remaining time for all in sprint tasks (incl. subtasks) is correct, ideal burndown (guideline) drawn a bit below than should be (given measuring working time left as # of people * 7 hrs/day * days remaining).
Two questions:
Thanks for clarifications in advance,
Aquarius.
You can configure the number of hours in a workday like explained here :
https://confluence.atlassian.com/display/JIRA/Configuring+Time+Tracking
Greenhopper should pick this up.
I found this helpful piece of information here : https://answers.atlassian.com/questions/69480/how-do-i-change-the-time-tracking-hours-per-day-from-8-to-10
:)