Question about JIRA Porfolio

Jason J December 20, 2016

Topic is JIRA Portfolio

Is there an ability in JIRA Portfolio to do the following in a single view.  This would allow us to assign resources according to their availability.

Project 1/ Sprint 1 (Active sprint)- Resource assigned 100 Percent of their time

Project 2 /Sprint 2 - (Active sprint) Resource assigned 100 Percent of their time

Project 1 /Sprint 3 - (Future sprint) Resource is working 20 percent of their time on 2 tasks  Can we assign them to work on the remaining 60 percent in this future sprint 3?

 

1 answer

0 votes
Bhushan Nagaraj
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
December 20, 2016

Hi Jason

JIRA Portfolio has the concept of teams. Each resource/team member can belong to multiple teams with a different availability for each team. For example, John can belong to team Mars, Venus and Jupiter. John has 38 hours availability per week. You can dedicate John 40% of the time to team Mars, 40% to team Venus and 30% to team Jupiter. Then at the Epic/Story level, you can set which team works on the task. Irrespective of which Sprint you schedule in, John's availability is considered as allocated.

Thanks

Bhushan

Suggest an answer

Log in or Sign up to answer