When an issue is scheduled in a future sprint and it is determined that it should be canceled should it be removed from the sprint? Will this keep it from showing on a sprint report as completed outside of the sprint?
If so, what is the proper order?
or
Thanks in advance,
Jay
You mention “future sprint”.
If indeed the issue is not in an active sprint then - drag out of the sprint (or remove the sprint from the field) and then cancel the story.
if it is in an active sprint then simply mark the story done with resolution of won’t do or canceled and let it fall thru the sprint naturally.
I believe if you clear the sprint field then it will be considered a change of scope for the sprint. Best to cancel/resolve the issue with a "won't do" or withdrawn resolution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
My recommendation:
1. Clear Sprint Field
2. Cancel Issue
You could look into some automation that clears any future sprints from an issue that's cancelled.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.