Proper way to cancel issue that is scheduled in a sprint?

When an issue is scheduled in a future sprint and it is determined that it should be canceled should it be removed from the sprint?  Will this keep it from showing on a sprint report as completed outside of the sprint?

If so, what is the proper order?

  1. Clear Sprint Field
  2. Cancel issue

or

  1. Cancel Issue
  2. Clear Sprint Field

Thanks in advance,

Jay

3 answers

1 accepted

0 votes
Answer accepted
Jack Community Leader Dec 11, 2019

You mention “future sprint”.

If indeed the issue is not in an active sprint then - drag out of the sprint (or remove the sprint from the field) and then cancel the story.

if it is in an active sprint then simply mark the story done with resolution of won’t do or canceled and let it fall thru the sprint naturally.

My recommendation:

1. Clear Sprint Field
2. Cancel Issue

You could look into some automation that clears any future sprints from an issue that's cancelled.

I believe if you clear the sprint field then it will be considered a change of scope for the sprint.  Best to cancel/resolve the issue with a "won't do" or withdrawn resolution.

Suggest an answer

Log in or Sign up to answer
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you