How do you configure Jira to check for any associated issues are open prior to moving to a done or completed status?

Example. I am using an issue type of Risk and associate it with a Story,Task,etc.  I would not want a story,ask,etc to move to a completed-done status until all associated Risks have been mitigate or an separate approval has been made to allow.

thanks you 

Dale

2 answers

0 votes
David Pinn September 11, 2017

Sometimes it's useful to prevent the closure of a risk until all of the mitigation tasks have been completed. I wrote a blog post about that last year: Using sub-tasks with risks. The article has some stuff that's specific to our product, but the principle is generally applicable.

0 votes
Joe Pitt
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 11, 2017

You can put a condition that all subtasks must be closed, but not another issue out of the box. There may be a plugin or scripting may do it. 

Dale Dean September 11, 2017

thank you!