Potential issues with time tracking legacy mode turned off

We're going to turn off the legacy time tracking mode so the Original Estimate field can be edited after any time is logged on. Do you know if there is any risk related with this action, like some reports may start behave incorrectly or whatever?

1 answer

The only problem i can think of is the velocity chart not working (i.e. if you have jira-agile enabled). Velocity chart takes into account the original estimate in its calculation;. So if you are allowing users to adjust it during middle of sprint then the chart will be non-representative.

Rahul

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 25, 2018 in Jira

Atlassian Research Workshop opportunity on Sep. 28th in Austin, TX

We're looking for participants for a workshop at Atlassian! We need Jira admins who have interesting custom workflows, issue views, or boards. Think you have a story to sha...

469 views 7 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you