Potential issues with time tracking legacy mode turned off

We're going to turn off the legacy time tracking mode so the Original Estimate field can be edited after any time is logged on. Do you know if there is any risk related with this action, like some reports may start behave incorrectly or whatever?

1 answer

The only problem i can think of is the velocity chart not working (i.e. if you have jira-agile enabled). Velocity chart takes into account the original estimate in its calculation;. So if you are allowing users to adjust it during middle of sprint then the chart will be non-representative.

Rahul

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Apr 17, 2018 in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

770 views 2 19
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you