Hi,

My project uses Fix Version as columns in our board, and our customer / product owner changes Fix Version + Priority on parent issues to plan the teams working priorities. We have Create post functions (with the JMWE add-on) that copy Fix Version and Priority from parents to subtasks.

When the pipeline is re-planned after some time, existing issues are moved around by changing these fields - but the sub task fields are not updated. Is it possible to run a post function after field changes, so that priority and Fix Version can be automatically updated on subtasks?

Alternatively it would also work to set up inheritance from the parent (only for this project, not globally), although it would be best if a subtask could change Fix Version without the parent changing.

I can't add paid add-ons, so keep solution suggestions to free add-ons or existing functionality please!

Greetings,
Tormod Tønnesen 

2 answers

Do you have Script runner available?

Unfortunately no.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,715 views 17 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you