Portfolio sets a resolution date in Jira after creating an Issue

Hi,

We are using Portolio since a couple of weeks. We created 3 Stories from Portfolio and the Issues created in Jira have as Resolution status "Unresolved" but we found out that it sets a Date resolution (see image attached). In the three Issues the created date coincides with the resolved date.resolution.png

Why this happens? How can we solve it?

We use Jira (server version 3.7.6).

Thank you.

Nuria

1 answer

0 votes

Could you log in as an Admin (Jira or System admin) and go to admin interface, Admin -> Issues -> Resolutions.

Do you have "Unresolved" on the list there?

Hi Nic,

No, I do not have Unresolved on the Resolutions list

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

2,755 views 11 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot