Portfolio for JIRA - Team availability / Absence question

If we assign a team availability of 20 to a team member and then record an absence of three days in one week for him, how many hours will Portfolio see when planning? 8 or 20?

2 answers

0 vote

8, assuming that working days are configured as standard Mon-Fri. It will take the weekly hours, divide by the number of working days (20 hours means 4 hours a day). If 3 days are off, then only 4 hours each on the remaining two days are left to be scheduled. 

Great, thank you!

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Posted Wednesday in Jira

Join our webinar: How 1B+ feature flag events helped us build the new Jira

Every time you release software, there's a bit of risk – that there's a bug, that something breaks, or that the feature doesn't resonate with customers. Feature flagging helps make high stakes s...

136 views 0 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you