Portfolio for JIRA - Team availability / Absence question

If we assign a team availability of 20 to a team member and then record an absence of three days in one week for him, how many hours will Portfolio see when planning? 8 or 20?

2 answers

This widget could not be displayed.

8, assuming that working days are configured as standard Mon-Fri. It will take the weekly hours, divide by the number of working days (20 hours means 4 hours a day). If 3 days are off, then only 4 hours each on the remaining two days are left to be scheduled. 

This widget could not be displayed.

Great, thank you!

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

197 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you