Portfolio for JIRA - Team availability / Absence question

If we assign a team availability of 20 to a team member and then record an absence of three days in one week for him, how many hours will Portfolio see when planning? 8 or 20?

2 answers

0 vote

8, assuming that working days are configured as standard Mon-Fri. It will take the weekly hours, divide by the number of working days (20 hours means 4 hours a day). If 3 days are off, then only 4 hours each on the remaining two days are left to be scheduled. 

Great, thank you!

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Posted 11 hours ago in Jira

We want to know what Jira Service Desk apps you're using!

Hi Community! My name is Amir and I’m on the Jira Service Desk product marketing team at Atlassian. Our team would love to understand how you’re leveraging our ecosystem for Jira Service Desk. Wha...

34 views 0 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you