I have a large number of items in my portfolio. I need to filter it to be able to edit (e.g. set dependencies) child items.

The very first item in my scope view has a scheduled start of 2/21/17 and a scheduled end of 3/7/17. That means all children items must complete during that timeframe, right?

When I select the More->Scheduled Range filter, and select a range of 2/1/17 to 3/31/17, I only see two of the 10+ child items.

Portfolio 2.2.2

1 answer

1 accepted

I was able to resolve this.  I had set an invalid dependency on one of the child items (it was dependent on the completion of it's parent).  That prevented the Portfolio scheduler from being able to schedule that task and all subsequent tasks that were dependent on it.  So although the the epic had a scheduled end date, it wasn't based on completion of all the child tasks.

I'm not sure why portfolio allowed me to set the invalid dependency or at least warn me about it, but in the end the mistake was mine.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Monday in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

713 views 6 13
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you