Portfolio: Remaining estimate

Artem Petrik July 12, 2016

A ticket was estimated as 64 hours. We've logged 22 hours in it. Progress bar in portfolio shows that we've completed 22 hours but remaining is still 64 hours.

 

Why doesn't progress update a remaining estimate in portfolio?

 

1 answer

0 votes
Allard van Helbergen
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 12, 2016

Hi Artem,

Thanks for your question. Do you fill in a remaining estimate when logging time? If no remaining effort is set on the issue in JIRA, the original estimate is considered as the remaining effort. Thus 22 hours logged and 64 hours left.

You can find the full details of progress calculation in our documentation. See https://confluence.atlassian.com/display/JIRAPortfolioCloud/Status+and+progress+tracking#Statusandprogresstracking-Timebased.

 

Best,
Allard 

 

Artem Petrik July 12, 2016

Yes, we have remaining estimate filled.

Please see the screenshots below

Screenshot 2016-07-13 11.21.40.png

Screenshot 2016-07-13 11.22.56.png

Allard van Helbergen
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 12, 2016

We'll need a bit more information to look into your specific issue. Please raise a support ticket here, https://support.atlassian.com/servicedesk/customer/portal/28.

Thanks,
Allard 