Portfolio Import CSV does not take all values, creates every time new issues, no update

I want to load Issues into Jira Portfolio out of an Excel file and later on update them. We have to do this several times, because we are in a basic phase of the project.   Two problems I am phasing

  1. I try to update existing issues in Jira, every time new issues are generated
  • It looks like I can generate links to Parent Initative
  • Attached the example CSV file and the Map Field file

 I try to load values into the fields  into Jira Portfolio

  • Attached csv.jpeg images show the CSV file (green works without problems) 
  • The config1 to 3.jpeg shows the config3.JPGconfig2.JPGconfig1.JPGcsv.JPGimport mapping

0 answers

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

22,619 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you