Portfolio-How to refresh Sprint list

I just stared using Portfolio 2.0, I used the wizard to connect it to our Board.  We have Sprints on the Board that are serving to group Stories for purposes other than scheduling into a release.  They're used as holding buckets to easily remember which Stories were deferred from a Release.  The Stories in each of these "non Sprint" Sprints may be in many Epics.  Is there any way to suppress these non-Sprint Sprints from coming into Portfolio?  I tried emptying one and then deleting it from the Board, but it is still showing in Portfolio. 

1 answer

1 accepted

Accepted Answer
0 votes

Hi Ericka,

Thanks for your question. Currently there is no way to suppress sprints from your connected boards. All sprints on your board will show in your plan.

When you delete a sprint it will be reflected in the schedule upon (re)calculation. However, due to technical limitations you will need to refresh your browser tab for the plan to fully reflect the deletion in all the drop-downs of the scope view.

I hope that answers your question.

Best,
Allard 

thank you very much for taking the time to help me!  much appreciated!

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 25, 2018 in Jira

Atlassian Research Workshop opportunity on Sep. 28th in Austin, TX

We're looking for participants for a workshop at Atlassian! We need Jira admins who have interesting custom workflows, issue views, or boards. Think you have a story to sha...

419 views 7 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you