  • Please validate and verify the issue with Burndown chart -Planned estimated efforts, Effort spent and Remaining efforts’ values are not captured/updated accurately, that is the issue in burn down chart in Jira?

Please validate and verify the issue with Burndown chart -Planned estimated efforts, Effort spent and Remaining efforts’ values are not captured/updated accurately, that is the issue in burn down chart in Jira?

8 answers

Is it a configuration issue?

0 votes

Looks like people have been adding/removing things in the sprint, and/or adjusting the remaining time directly. I'd recommend finding the issues that are causing the spikes and working out why they've been doing it

Thanks much, Nic.

Please eloborate on "adjusting the remaining time directly."

0 votes

You can choose "adjust remaining time" in the worklogs, and/or edit the time in the edit screens.

But in JIRA; date/time of a History entry matches that of when it was created. However, the date/time of a Work Log entry matches that of when the work was conducted.

0 votes

Yes. I'm not sure how that's relevant though. Look at how the issues have been changed and work logged against them.

Hi Nazeer,

Not sure I completely understand your question, but you might want to look into burn up charts instead of relying on burn down charts.

Below is one of the scenarios for the issue in burndown chart;

What we missed in our initial planning was creating of testing subtasks in parent issue but one can argue subtasking anyways hasn’t happened for stories.

Ideally a task should not have estimated effort >1d which helps in measuring progress. Is it so?

Additionally total effort for a parent story should also consider effort for testing the feature which again need to be estimated during planning meeting based on the scope, complexity of feature.

Please let me know your suggestions.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,121 views 13 19
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot