Planning Time at the month level (as opposed to day level)

Carlo Bonamico November 20, 2012

With Tempo, it is normally possible to plan time for a user on a Project or Issue by specifying the hours per day for either

  • a single day
  • a range of dates (in which case the same amount of time is planned for every day)

I would need to be able to plan time at the month level (e.g. this user will spend 5 days or 40 hours on this issue/project during December 2012).

I that possible with the plugin? would it be possible by using some API / custom script?

Thanks

1 answer

1 accepted

0 votes
Answer accepted
Viðar Svansson [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 21, 2012

Suggest an answer

Log in or Sign up to answer