Plan time in Tempo - automatically add to sprints

Hi, we would like to plan our resources in Tempo plugin and have the issues automatically added to sprints in Greenhoper. is this possible?

Or, what would be the best workflow to use when working with both Tempo and Greenhoper?

Thanks

1 answer

1 accepted

This widget could not be displayed.

It is not possible to. You first add issues to sprint and the plan your resources.

In GreenHopper, you can select the issue and from the cog-wheel (keyboard shortcut: '.'), select 'Plan Time'.

Thanks for reply. Is there a way to see in Greenhoper sprint which issues have already been planned?

Is this feature in the works? For us, best way would be to auto sort the issues in sprint by planned date...

No not yet, unfortunately.

I don't think we have this exact feature planned but we are working on various integrations with GreenHopper. Feel free to create new feature requests in our issue tracker.

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

112 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you