Hi Guys,
I want to create a pie chart (or a very clean table) to show the time spent/logged by the assignees yesterday
I tried to use a Workload Pie Chart Report, but it will show the time spent from first day of the project.
You can use a filter, but i could not find a way to create a filter that sets the time period
Any idea?
Thanks!
You can edit the query in the filter by using JQL similar to below:
status changed to DONE after startOfDay() -1 OR status changed to "IN PROGRESS" after startOfDay() -1
Better Excel Plugin has an export template called worklog-analysis.xlsx that exports worklogs to an Excel sheets and does configurable multi-dimensional analysis on them.
You could easily modify that to your needs:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your answer
Is there a way to create a filter that just sets the time range to YESTERDAY ?
In this way i could use a Workload Pie Chart Report that tracks (Time Spent) by Assignee within that period
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Not possible out of the box. Filter will always get you the latest information, although you can search for issues updated/created yesterday and so on. The data it returns will be current.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
On Cloud, the only option will be to use the Tempo plugin, I guess.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.