Original estimate to sub-tasks, why it affects the Story Original estimate?

Hi All,

I Have  scenario where:

  1. First, in a very initial stage i'm giving an estimation on the epic level in time units of weeks
  2. Then, on the story level, in the release planning i'm estimating the stories in time units of days
  3. Finally in the sprint planning a detailed estimation in hours

So now i'm having an issue, if i'm giving an original est. on both stories and their Sub-tasks the estimated field on the story level is updated to the sum of the story+sus-tasks estimation.

I would like to maintain the org. est. of the story and see kind of a correct est. for the sum taken from the sub-tasks(And off course, all should be aggregated to the Epic level as well).

So currently to achieve that i'm not updating estimates on the sub-tasks level, only using Time tracking. But i'm afraid this will affect me as i'm using the OOB reports like the burndown and velocity charts.

Any advise?  

Thanks

Shirley

2 answers

Dear Shirley, I have exactly the same problem like you. Have you found a solution yet? I read you need to write a code with the scriptRunner add-on to achieve this, but i'm not sure how to do it. Have you tried this option?

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Amir Kazemi
Posted 3 hours ago in Jira

We want to know what Jira Service Desk apps you're using!

Hi Community! My name is Amir and I’m on the Jira Service Desk product marketing team at Atlassian. Our team would love to understand how you’re leveraging our ecosystem for Jira Service Desk. Wha...

15 views 0 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you