Nikoletta January 28, 2015

Dear Atlassian Team,

Would you please advise where and how to change the settings,  so that we can estimate any task? 

Task estimation isn't possible currently, only in the agile backlog (Plan) view (and not even for all the tasks). 

Thanks for your help in advance. 

Best, 

Nikoletta

 

 

1 answer

1 accepted

0 votes
Answer accepted
Philippe Aubin
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 28, 2015

You need to add the ''time tracking'' field on your issue screen. 

 

See: https://confluence.atlassian.com/display/JIRA/Defining+a+Screen

Nikoletta January 28, 2015

Hi Philippe, Thanks for your help. This and changing the agile board configuration for Estimation seem to be the solution for us. Testing now.