Original and remaining estimate

Dear Atlassian Team,

Would you please advise where and how to change the settings,  so that we can estimate any task? 

Task estimation isn't possible currently, only in the agile backlog (Plan) view (and not even for all the tasks). 

Thanks for your help in advance. 

Best, 

Nikoletta

 

 

1 answer

1 accepted

You need to add the ''time tracking'' field on your issue screen. 

 

See: https://confluence.atlassian.com/display/JIRA/Defining+a+Screen

Hi Philippe, Thanks for your help. This and changing the agile board configuration for Estimation seem to be the solution for us. Testing now.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

351 views 1 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you