Original Estimation

Michael Fritz February 13, 2015

Hi,

I have a project where every task was estimated before the project started. I want to have a report that compares the tracked time to the estimated time in order to track the projects rentability - just normal project management stuff.

How can I achieve this? We have Time Tracking module and I thought this was a part of it, but apparently I cannot add the estimations to the tickets?

While editing the tickets I cannot add an estimation, only if I work-log minimum 1m (which is ridiculous).

 

Please help!

2 answers

1 vote
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 13, 2015

Have you got the timetracking field on the "edit" screen for the issues?

0 votes
Michael Fritz February 13, 2015

Ok, your question got me to the answer. The field was somehow hidden by the Agile thingy. I could activate it by clicking through "screens".