Original Estimation

Hi,

I have a project where every task was estimated before the project started. I want to have a report that compares the tracked time to the estimated time in order to track the projects rentability - just normal project management stuff.

How can I achieve this? We have Time Tracking module and I thought this was a part of it, but apparently I cannot add the estimations to the tickets?

While editing the tickets I cannot add an estimation, only if I work-log minimum 1m (which is ridiculous).

 

Please help!

2 answers

This widget could not be displayed.

Have you got the timetracking field on the "edit" screen for the issues?

This widget could not be displayed.

Ok, your question got me to the answer. The field was somehow hidden by the Agile thingy. I could activate it by clicking through "screens".

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

135 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you