One project; multiple teams, running parallel sprints Edited

So on a project, different team members have different task (timeline). How can the project notify the next team member that his or her task is up next to complete? Is this possible?

 

Example: when Sam completes his task in the project he and his team is working on , how to I setup to alert Amy that it is her turn to take the info gathered by Sam and complete her part?

 

Thanks in advance for your input!!!

1 answer

1 accepted

There are multiple options:

  • Sam will assign completed task to Amy with comment that she can proceed with her task
  • Amy will be added to 'watchers' field on Sam's task so she will be notified about changes on Sam's tasks

Or do you need something smarter? :)

That will work!

Thank You for your imput!!

you're welcome, could you accept the answer, please?

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

73 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you