No story update report

V G April 23, 2017

Hi,

 

How do I creaate a report for stories which are not updated for past 3 days. Key issues, team is not updating JIRA on regular basis. How can I bring decipline within the team.

 

Thanks

1 answer

0 votes
Sam Hall
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 23, 2017

You could report the issues using a JQL query like:

issuetype = story AND updated <= -3d and resolution = Unresolved

That would show all stories that are not resolved, and were last updated more than 3 days ago.

V G May 4, 2017

Thanks a lot