No Estimate for Custom Issue Type in Sprint Planning Phase

James Gill May 24, 2017

For some reason when planning a Sprint that contains Custom Issue Types, the Custom Issues that I have created do not allow me to add an Estimate as part of the Sprint Planning Phase, however the 'normal' Issue Types (Task, etc) allow me to enter an Estimate.

I've double checked to make sure that my Custom Issue is using the same Field Scheme, Issue Type Scheme, and Screen Scheme (See attached) as the Task that allows me to enter an Estimate, yet for some reason the Estimate field does not appear.  Issue Type Configuration.png

1 answer

0 votes
Steven F Behnke
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 24, 2017

The field Story Points is context-limited to Story and Epic by default. Change the configuration scheme.

James Gill May 26, 2017

Cool, I'll give that try.