New lines into worklog

Marek Rasovsky September 16, 2012

I would like to ask on one thing. Is there a possibility to add new lines into worklog? There are now:

- time spent
- date started
- remaining estimate
- and work desription

We would like to have here 2 more text lines here, but I dont know, if is that even possible.

Could anybody answer me?

Thanks in advance and sorry for my bad english :-) . I m not native speaker :-)

1 answer

1 accepted

1 vote
Answer accepted
John Chin
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 3, 2012

Hi Marek, this feature is not available in JIRA currently. There is an open ticket https://jira.atlassian.com/browse/JRA-4939 raise as Improvement. You could vote as popularity of issue and add your in the watchlist to keep you updated.

Regards, John