We have large sprints with over 200 issues in it. Sometimes when scrum masters are prioritising they felt the need to move issues to the top/bottom of current sprint without dragging and dropping through 200+ issues.

I know with right click you can move it to top/bottom of backlog, but can the same functionality be implemented to move issues to top/bottom of the same sprint?

Rahul

1 answer

1 accepted

I think i found the answer in  keyboard shortcuts.

S and B for moving to bottom of sprint

S and then T for moving it to top of the same sprint.

 

Rahul

 

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,308 views 14 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot