Moving issues to bottom of backlog without dragging them

Hi

We have large sprints with over 200 issues in it. Sometimes when scrum masters are prioritising they felt the need to move issues to the top/bottom of current sprint without dragging and dropping through 200+ issues.

I know with right click you can move it to top/bottom of backlog, but can the same functionality be implemented to move issues to top/bottom of the same sprint?

Rahul

1 answer

1 accepted

This widget could not be displayed.

I think i found the answer in  keyboard shortcuts.

S and B for moving to bottom of sprint

S and then T for moving it to top of the same sprint.

 

Rahul

 

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted yesterday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

82 views 1 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you