Move issue error "The issue type selected is invalid."

Hansoo Bae July 3, 2016

When I try to move the issue from Project A to B,

this message is showing and cannot move the issues.

 

and this is also different for target issue type, 

for example, Task to Epic is ok, but Task to Task issue type is not working. 

 

I am not sure why this happens, anyone have any idea? 

2 answers

1 accepted

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 3, 2016

Usually means the target issue type doesn't exist in the target project.  Check that first - can you create issues of type "task" in the target project?

Hansoo Bae July 3, 2016

I found the solution for the problem. Thanks anyway. 

 

Hansoo Bae July 3, 2016

FYI, There was a task type in the targe project. smile