Make 0 Remaining Estimate Keeping Original estimate as it was

Gor Greyan
Contributor
November 6, 2024

Hi Dear Colleagues,
I need the following.
When sub-task goes to Done, to make 0 Remaining Estimate keeping the Original estimate as it was, is it possible?

1 answer

1 accepted

0 votes
Answer accepted
Kseniia Trushnikova
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 13, 2024

Hi @Gor Greyan,

Sure, try to add the Update Issue Field post function to the transition to Done:

Screenshot 2024-11-13 at 18.43.08.png

It clears only the Remaining Estimate field value.

Gor Greyan
Contributor
November 15, 2024

@Kseniia TrushnikovaThank You very much, it works.

Like Kseniia Trushnikova likes this