Hi all

When my colleagues log work on project A, i can't see it when i look at the overview of project A (i am admin). But when i look at their user overview, the hours logged on project A are visible. Other prjects are ok, it's only project A. I really can't find the problem.

Thanks!

2 answers

1 accepted

0 votes
Answer accepted
Marie Daly August 25, 2014

I found it: in order to view the contribution of other users, you need to be in the Tempo Project Managers role for the given project.

0 votes
Susanne Götz [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 25, 2014

Hi Marie,

you are correct, I was just reading your question when you were adding the comment :)