Logged effort is not appearing in the Time spent field

Hi,

I am using the workload pie gadget in JIRA. I have configured it for assignee and on Time spent. However, if time spent field is empty but aggregate time spent field has some values, the chart doesn't pick it up. My question is:

 

1. In what scenario is time spent field is empty and Aggregate time spent field has values?

2. Is there a way to configure Workload pie chart on aggregate time spent?

1 answer

This widget could not be displayed.

I realized that I need to have sub-tasks in the filter to allow the gadget to pick up the time spent from the sub-tasks of the stories. Time spent field just picks the time logged on the story and not on its sub-tasks, while Aggregate time spent picks everything.

ideally, workload pie should allow aggregate time spent as one of the option.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

203 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you