Linking Issues with Sprints

felix_schoch
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 23, 2024

Hello, I extracted the tables form jira and added it to our DWH. I want to create a detailed sprint report in tableau. This is the ERD I found:

https://docs.google.com/presentation/d/1UPq2CWnqQpbjLxkTrcWvAekaZ0o0OdzXODTVmUXeGvs/edit#slide=id.g1379aea0489_0_591

My question now is how can I link the issues and the sprints?

If I link the issue to the board and the board to the sprint, it doesnt give the results that I am looking for, which makes sense if the board is always the same, but what other way could work?

 

Thanks a lot!

1 answer

0 votes
Fabio Racobaldo _Herzum_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 4, 2024

Hi @felix_schoch and welcome,

you should drag and drop an existing issue to an active sprint within your board.

https://support.atlassian.com/jira-software-cloud/docs/add-issues-to-an-active-sprint/

A board has one or more sprints and issues are in the backlog.