Linkage between remaining effort of parent story and its sub tasks

Hi,

 

Hi. I have created a story and created 5 sub tasks under it. So, when I add efforts to those sub tasks, does the original estimation field of the parent story get updated with the sum of the efforts of the sub tasks? 

 

For an example - 

I am creating a parent story as "X", and adding 5 sub tasks with below efforts

x.1 - 2h

x.2 - 4h

x.3 - 2h

x.4 - 1h

x.5 - 6h

 

So, after adding these efforts to sub tasks, will the original estimation field of the parent task get updated as 15h?

 

Cheers,

Hansi

1 answer

I am using Jira Server (v8.5) and this does work.  There is a checkbox on the Story under the Time Tracking section to "Include sub-tasks".  See screenshot:

 

image001.png

Hi Pete, 

Thanks a lot for getting back to me. I am using the cloud version, I couldn't find "Include Sub Tasks" check box in time tracking section. Is there any specific way to set-up jira cloud version to add effort of sub tasks to parent story? Really appreciate your support on this

Cheers,

Hansi

Apparently it's a bug in the "New Issue View".  See here:

https://jira.atlassian.com/browse/JRACLOUD-69587

But you should be able to switch the new view off:

https://confluence.atlassian.com/jiracorecloud/the-new-jira-issue-view-938040503.html

Suggest an answer

Log in or Sign up to answer
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you