Kanban Board does not show story subtasks under the stories

Ruben Sadoyan June 12, 2014

Hi guys.

Jira 4.4.5

kanban board does not show story children (subtasks) below the story. Somehow subtasks live their own lives and are not shown with their parents. What is wrong?

Thanks in advance,

Aquarius.

3 answers

2 votes
Henning Tietgens
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 12, 2014

Did your filter for the board finds the subtasks? It should, if you want to see the subtasks.

1 vote
Ruben Sadoyan June 12, 2014

Filter finds subtasks, actually managed to show them and want to make Jira base swimlines on stories so that subtasks are shown groupped by story or parent ticket, but it is impossible neither in Kanban board template configuration nor in scrum.

Is this because of old version of Jira or something else is wrong?

0 votes
Peter Van de Voorde
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 12, 2014

Hi Aquarius,

Are you basing your swimlanes on stories or something else?

Does the board sub filter filter out your sub tasks (look at the bottom of the general configuration page to see the sub filter).