Hi - we are using a basic kanban for a short term project to keep a couple groups collaborating. We use Tasks/Stories and SubTasks alot in SCRUM Based Projects. In this case, we would like to have the SubTasks Grouped under the Parent rather than loose in the board. In a Scrup Sprint, it usually is grouped and can be minimised or maximized. Anyone know if we can do this and how?
Thanks,
Morgan
Hi Morgan,
There was a similar request raised some time ago and there was some guidance in the Suggestion raised for it which was to add the following to your board's query:
issueType in standardIssueTypes()
You will see the following in the quick view window for the issue to the right:
If you find a more elegant way let me know!
Cheers,
Branden