KanBan Release Process

Rethabile Morena September 11, 2014

Good day,

 

Please note that some, and not all closed issues on our Kanban board go to the 'Released' Tab.

 

How do we achieve this?

 

Regards

Rethabile

2 answers

0 votes
Timothy Boyer May 20, 2015

I am also interested in this topic.

I have defined the columns of our Kanban, including "Done". Now, I want to Release only certain items and there does not seem to be a way to do this.

I have explored Versions under Project Administration, but that does not actually release items off my Kanban.

Any help is appreciated.

#jira, #agile, #kanban

0 votes
Kevin Maes September 11, 2014

hi,

 

Could you give some more info. What board setup are you using? I'm guessing the standard with todo - in progress- done.

You can release by clicking above the done column on the hyperlink: 'release ...' This gives you a popup to create a new version with releasedate etc, Or even if you have a bamboo instance linked, you could start a release build from here as well.

 

Hope this helps, please elaborate if this doesn't answer your question.

 

Regards

Kevin

 