Anyone know why this happens? I have a 30m estimate, logged 30m of work, and still have 30m remaining... Why does this happen?

4 answers

0 votes
Viðar Svansson
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 21, 2012

Hi Marc,

Remaining estimates were not always working as expected with the new JIRA 5.1 but was fixed in latest Tempo version. Let me know if this might be your case. Then you should be good by updating to Tempo 7.2.4.

Cheers,
Viðar
Tempo

0 votes
Marc Addeo August 20, 2012

I'm using Tempo.

0 votes
Thiago Ribeiro
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 20, 2012

Have you got in contact with Tempo?

This must be a misconfiguration on Jira and Tempo.

0 votes
Thiago Ribeiro
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 20, 2012

Hi Marc,

Are you using Jira Time Tracking or Tempo?

When was the time logged on the issue?