Jira Structure Resource Leveling uses random order

Edited

I am using Jira Structure with Gantt and trying to schedule tickets on the project with resource levelling. Instead of levelling one-by-one, it places first a ticket from the end of a structure, then some random ticket from the middle, etc.

Level priority is the same for all issues.

Levelling priority in Gantt config is "Store in Gantt chart". And I have no option there to change it on a Rank or Index (no such things in the dropdown).

So, my questions are:

  1. What I am doing wrong?
  2. How to add Structure index in Levelling priority? (I suppose it can solve the problem)

1 answer

0 votes

Hello @ayub shami 

It should be possible to level resources based on Rank & Structure Index - both options were added to the Leveling Priority section of the chart's settings in Structure.Gantt 2.4. So if you're using an older version, an upgrade would be required.

I hope this helps. If you need further assistance, please contact us directly at support.almworks.com and we'll get back to you shortly.

Best regards,
Stepan Kholodov
ALM Works

Suggest an answer

Log in or Sign up to answer
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you