Jira Portfilio - Schedules not working?

Using JIRA Portfolio for Cloud

Have created a number of initiatives, epics, and assigned issues and resources to them. However, when viewing the Schedule down below, which should operate like a Gantt Chart, it is not showing a number of the Epics at all. There seems to be no rhyme or reason why one epic is shown and another is not.

Any tips and tricks? The entire "schedule" section seems very half-baked and difficult to configure in a useful manner.

2 answers

In case the schedule shows text similar to "The current result set does not contain any stories", then you need to create teams.

Once teams are created the scheduler view starts showing data as a Gantt Chart

Not the case. I already have teams, but still don't see the schedule working as it should.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

561 views 1 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you