Folks – I have a project where items in the same status – Open – has different screens. Sometimes, the transition Start Progress can be chosen from the screen. Sometimes not.
I just ran a database integrity checker and everything passed. I am about to embark on a study on the Advanced Workflow configuration as suggested by Atlassian Support.
Does anyone have any other suggestions?
Thanks – Janet
I would look at the workflow conditions. If you're using the standard workflow it comes with a "current assignee" condition, which means that only the current assignee can trigger that workflow transition.
Fabulous Christian ... Yes, now I see the condition.
Thank you ...