Jira Gantt Chart plugin marked an issue to "Over-capacity"

Screen Shot 2014-11-18 at 19.47.46.png

As you can see from the image above, I have an epic called "Setting up office environment" , the duration of this task, as you can see in the yellow box, is "3 working days".

The epic contains 3 issues:

  1. SW-33: Estimated 2 days 2h 36 minutes and done by me exactly on time.
  2. SW-4: Again, Estimated 2 days 2h 36 minutes and done by my college exactly on time.
  3. SW-14: Estimate as 2 hours and done by me exactly on time.

The point is SW-33 and SW-4 done simultaneity by me and my college together in the same days.

Images are as below, from left: SW-33, SW-4, SW-14

Screen Shot 2014-11-18 at 19.53.53.png

_______________________________________________________________

 

Screen Shot 2014-11-18 at 19.54.09.png

________________________________________________________________

Screen Shot 2014-11-18 at 19.54.26.png

 

The problem is that the Gantt-chart plugin marked the epic as "Over-capacity: planned 166% allocated work, current need: 0%", which is wrong . Actually I think its calculated as followings:

((∑Original estimates)/(Duration))*100

In this case

((0.33+2.33+2.33)/(3))*100=166%

Which is wrong, because the task is not over capacity and the epic distributed between 2 people and it can be done in 3 days. Because the two 2.33s in the above calculation were done simulantely , I think it must be calculated as this (it can be rounded or calculated other ways)

((0.33+2.33)/(3))*100

What's wrong ? Is it really the problem ?

4 answers

Hi Michel,

you're correct: there is no distinction between different assignees, currently. I have placed that topic to be fixed within coming version 3.1.6. As epics are kind of containers of issues possibly belonging to different team members, a single indicator of over-capacity does not really make sense within this context: but per assignee, they are useful.

Kind regards,
Frank

Fixed within Gantt-Chart pre-v3.1.6, available for download from my server at http://www.polscheit.de/plugins/jira/gantt-chart/gantt-3.1.6-JIRA6.jar: download JAR-file and install it via "upload" button on JIRA's page "manage add-ons" as system admin.

Kind regards,
Frank 

Thanks dear @Frank Polscheit , but it didn't solved the problem, the over-capacity errror still there. What do you suggest ?

Dear @Frank Polscheit , I'll be glad if you can answer this question :)

Dear @Frank Polscheit,

So many thanks for great support and time you spent on this issue. 

I've updated the module and now it shows Version: 3.1.6-JIRA6 in the Admin panel. But the problem still exists on the gantt chart. (It still shows over capacity for the epic)

I tried reindexing + log-out and log-in but no difference.

What do you suggest? 

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,675 views 18 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you