Hi,
I'm trying to query in JIRA for items that are not estimated COMPLETELY.
What do I mean:
Especially the last two items I don't know how to query - is there a way to do that?
Hi Paul,
Sadly you cannot achieve the desired search using standard features on Jira, you must go for a third-party app instead. Using i.e. JQL Booster Pack you can type the following:
1) If it is a Story it has to have a Story Point Estimate
type = Story AND "Story Points" IS EMPTY
2) If it has sub-tasks all subtasks are estimated (in time)
type = Story AND issue IN parentOf(' type IN subTaskIssueTypes() AND originalEstimate IS EMPTY ')
3) If it has no sub-tasks the item has a time estimate on it
type = Story ANDissue
NOT
IN
hasSubtasks()
AND originalEstimate IS EMPTY
1,2,3) All together
type = Story AND ( "Story Points" IS EMPTY OR issue IN parentOf(' type IN subTaskIssueTypes() AND originalEstimate IS EMPTY ') OR (issue
NOT
IN
hasSubtasks()
AND originalEstimate IS EMPTY) )
(*) Note that this is just an example, you must tune above query to fit your needs.
Using this app you can also query other issues relations, check:
References: