How do I set a status to approved if an issue has a high priority upon being created Thanks

1 answer

1 accepted

0 votes
Answer accepted
MB
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 2, 2013

You have several ways to do this. You can create an Event Listener or a Post Function. In both ways, you'll have to perform a transition of that newly created issue which will transit that issue into the destination status. Here is an article showing how to do that: Performing Issue Operations (more precisely, the section "Transitioning an existing Issue").